The project involved the design of pre-cast gravity retaining walls for a ramp and stair access scheme, partially replacing the client’s original contiguous piled wall design. It also included the redesign of the contiguous piled wall that was ultimately adopted.

Our Role

CaSE was employed as the permanent works designer for the contractor’s alternative design.

Location
United Kingdom
Project Value
GBP 23M
Contractor
Wills Bros Civil Engineering Ltd